Canadian Manufacturing

Bruce Power’s Unit 1 sends power to grid for first time in 15 years

by Dan Ilika   

Procurement Energy Bruce Nuclear bruce power nuclear energy Ontario Power Authority OPA


Cost involved in getting first two units back online alone expected to be upwards of $4.8-billion

TIVERTON, Ont.—Bruce Power says the Unit 1 reactor at its nuclear facility bearing the same name is back online after almost 15 years of dormancy.

The revitalization project was aimed at refurbishing the decades-old nuclear plant, with restarts of Units 1 and 2, an overhaul to Unit 3 and the replacement of the steam generators at Unit 4.

According to the Ontario Power Authority, the original $4.25-billion price tag for reworking the four reactors in the facility’s Bruce A has now ballooned to almost $6-billion.

The cost involved in getting the first two units back online alone is expected to be upwards of $4.8-billion.

Advertisement

As outlined by Bruce Power in August, it will be responsible for all costs exceeding $3.4-billion.

With synchronization of Unit 1 now complete, final planned commissioning activities will be carried out on Unit 1, including safety system shutdown testing, according to the privately-held power generator.

The company says its Unit 2 is on track to return to operations in the fourth quarter of this year.

Unit 2 was originally scheduled for completion in early July.

The company says Units 1 and 2 will produce enough electricity to power cities the size of Ottawa and London, Ont., combined.

The return to service of Units 1 and 2 will bring the Bruce Power site back to its eight-unit capacity, according to Bruce Power.

Advertisement

Stories continue below