Canadian Manufacturing

Fukushima Dai’ichi power outage leaves three fuel pools without cooling for hours

by The Associated Press    

Canadian Manufacturing
Manufacturing Energy earthquake and tsunami Fukushima fukushima dai-ichi Fukushima Dai-ichi nuclear power plant Fukushima Dai-ichi plant Fukushima Daiichi Nuclear Power Station Fukushima disaster japan tsunami March 2011 earthquake and tsunami nuclear energy nuclear reactor TEPCO Tokyo Electric Power Co. tsunami


Will remain safe for at least four days without fresh cooling water

TOKYO—A power failure at Japan’s tsunami-damaged nuclear plant on Monday night has left three fuel storage pools without fresh cooling water for hours, the plant’s operator said.

Tokyo Electric Power Co.(TEPCO) said the power failure at the Fukushima Dai-ichi plant was brief at its command centre but continued for hours at three of the seven fuel storage pools and at several other facilities, including one that treats water contaminated with radioactivity.

TEPCO said the reactors were unaffected and no other abnormalities were found. TEPCO spokesman Takeo Iwamoto said the utility plans to restore power to the pool cooling systems as soon as it can determine the cause of the failure.

The utility said the nuclear fuel stored in the pools will remain safe for at least four days without fresh cooling water.

Advertisement

The March 11, 2011, earthquake and tsunami destroyed the plant’s power and cooling systems, causing three reactor cores to melt and fuel storage pools to overheat. The plant is now using makeshift systems.

Advertisement

Stories continue below

Print this page

Related Stories