Nova Scotia to pay ‘next to nothing’ for energy from $11.6B Muskrat Falls project

by Michael MacDonald, The Canadian Press   

Cleantech Canada
Financing Operations Cleantech Energy Infrastructure Public Sector


"Boondoggle" has begun creeping into the lexicon surrounding the delayed, over-budget hydro site and, according to Nalcor's CEO, a deal with Nova Scotia utility Emera is one of the reasons

An aerial view of the spillway at the Muskrat Falls hydro site. PHOTO: Nalcor Energy

An aerial view of the spillway at the Muskrat Falls hydro site. Earlier this week Stan Marshall said if the dam’s reservoir is not flooded the construction site could be inundated. PHOTO: Nalcor Energy

HALIFAX—Nova Scotia will be getting electricity for “next to nothing” when the Muskrat Falls hydroelectric project in Labrador starts producing energy, the man in charge of the megaproject says.

Nalcor Energy CEO Stan Marshall said the poor arrangement with Halifax-based Emera Inc. is one of the reasons the $11.4-billion Muskrat Falls project has proven to be a bad deal for Newfoundland and Labrador.

He said Nalcor is talking with Emera about changing the terms of existing contracts for the Maritime Link, the 170-kilometre subsea cable that will eventually carry electricity from Newfoundland to Cape Breton. Emera is paying for the $1.6 billion link.

“We only need about one third of (the electricity) on the island (Newfoundland),” Marshall said in an interview this week with The Canadian Press.

Advertisement

“So what do we do with the other two thirds? To get it to market, we gave one third to Nova Scotia for 35 years, for nothing—other than it is in return for building the (Maritime Link). The remaining one third was supposed to be sold into the market at a big profit, but energy prices have collapsed in the northeast, and it will be sold for next to nothing.”


Related: Muskrat Falls construction site could be inundated if reservoir not flooded soon
As a result, Marshall said, the project will be an economic burden for Newfoundland and Labrador for at least the next four years.

“This is a project that should not have been done because it’s too big for the needs of the province,” he said. “We took a risk on what energy prices would be, and we’ve lost the bet.”

According to the Emera Newfoundland and Labrador website, the Maritime Link Project is a 35-year investment equal to 20 per cent of the total cost of the Muskrat Falls project and the Maritime Link, in exchange for 20 percent of the electricity from Muskrat Falls.

The company says the link will help meet Canadian federal regulations requiring a 50 per cent reduction in coal emissions by 2030 and Nova Scotia regulations requiring 40 percent renewable energy by 2020.

Emera and the Nova Scotia energy department did not respond to requests for interviews.

Marshall was hired to take over the delayed and over-budget project in April after the Newfoundland and Labrador government determined Nalcor, a Crown corporation, had not provided proper oversight.

In June, Marshall agreed when asked if Muskrat Falls had become a “boondoggle,” saying the project was based on faulty, high-risk assumptions.

Still, Marshall said he remains optimistic he can mitigate some of the economic damage over the long term.

The federal government’s bid to have every province take part in some form of carbon pricing could help Muskrat Falls, particularly in the context of new carbon taxes, he said.

“A carbon tax should make this energy much more attractive to others, and we should get a higher price,” Marshall said. “With our four- to five-year horizon, I don’t think it will go from a burden to an asset … (But) our objective is to reduce the impact.”

As well, he said there are plans in the works to reconfigure parts of Nalcor, and he said the corporation will focus on signing more “firm energy” contracts with customers looking for 10- and 20-year commitments.